After attempting to use Microsoft Test Manager 2010 for an iteration, we quickly decided not to use it. Here is why.

About 3 years ago we finally managed to stop using HP Quality Center (AKA Test Director). We started managing our test cases and bugs as work items in Microsoft Team Foundation Server (TFS). The brilliance behind this transition was that it gave us the ability to attach our tests and bugs to the iteration’s Features/Stories and Tasks. This meant, as Features move in and out of iterations, the related tests and bugs follow; a beautiful thing! Additional benefits are, 1.) Programmers and BAs can easily review our test cases and write reports based on their execution status and, 2.) no more attempting to synch the TFS Features to Quality Center Requirements…the horror! I totally hated that!

It turns out, Microsoft Test Manager 2010, which sits on Microsoft TFS, took away many of the above TFS benefits and added as much overhead as Quality Center.

Stuff We Didn’t Like About Microsoft Test Manager 2010:

  • Before one can write tests, one must set up a Test Suite. Test Suites do not update when the Feature set changes. Thus, one must manually keep one’s Test Suite synched with one’s iteration. To further frustrate, without customization, Test Manager does not let one write test cases for Task work items.
  • Test cases in Test Manager follow a different workflow than those of TFS. The result is, nobody on your team can see which of your tests pass or fail unless they open Test Manager, which they probably don’t have a license for (unless they are testers). The reasoning behind this is probably Test Manager’s test cases can have test case run execution history (e.g., TestA could be passed in one build and failed in another build at the same time ). Test case run execution history is actually cool. In fact, it was one of the biggest motivators for us to try Test Manager. However, we were hoping Test Manager would trickle down the results to TFS so the whole team could benefit.
  • One of the most annoying parts of our Test Manager trial may have been its usability and performance. The screens frequently hung, causing some testers to force quit and re-launch. The navigation was also awkward. It took too many clicks to get anything done.
  • To update the execution status of Test Manager tests, one must go through the ridiculous test case executor. This is the thing that shows you each test case step and asks you for a pass/fail result. I can’t imagine anyone actually testing like this. Quality Center had something similar but provided an alternate method of updating execution status (i.e., one could bulk update via a grid).
  • Our other gripe about updating the execution status of Test Manager tests is that the test case “summary” does not show. Most testers like to write their test cases as fragments, using the test case work item’s free-form summary tab. The summary tab is preferred over the grid, which forces tests into individual steps with expected results. The big joke is, if you write your tests in the summary tab, it is not possible to see them while running the silly test case executor. So you are presented with a blank test step and asked if it passes or fails.

Stuff We Think We Like About Microsoft Test Manager 2010:

There are two things some project teams are planning on using Test Manager for in the near future:
  • Calling our CodedUI test methods and passing in parameters. According the idealistic demo I saw at the Stareast Microsoft booth, this allows manual testers to write/execute automated tests without coding.
  • Using test case run execution for regression testing.

Conclusion:

I guess TFS's simple work item model fits our needs for flexible lightweight test documentation with little administrative overhead. Maybe someone can convince me otherwise.

Many testers have chosen to make their jobs stressful by taking on more responsibilities than they should, obscuring their skills with those of others on their teams. Choosing to make your job less stressful will not only help you enjoy testing, it will also allow you to focus on testing, and improve your standing as a test leader. Here are some things I’ve learned over the years…

  • When people ask me “Did you QA Certify this for production?”, I remind them the question of when to ship is a business decision, but I can tell them much of what they need to know (e.g., how it currently works under certain conditions, what bugs exist) to make that business decision.
  • When I hear users complain about the product not working for them due to the way it was designed, I feel empathy for the users….then I remind myself that I never tell BAs/devs how to build the product or what it should do.
  • When I’m faced with really scary technical things to test, I turn to my team. I only have to look stupid to the first person I talk to, because by the time I get to the second person, at least I have what I learned from the first. As I continue to share my test ideas, they gradually change from lame to sophisticated. Soon, I realize everybody else on my team was just as confused as I was.
  • Crunch time. I expect it. I chillax at the beginning of an iteration and work harder/longer towards the end. I maintain my work/life balance by keeping my personal calendar free right before and after a production release. Working late with other team members is often just as fun as spending a quiet evening at home with my wife (don’t worry, she doesn’t read my blog).
  • Too much to test! Too little time! This one still stresses me out on occasion. But when I’m thinking rationally, I pose the question to my BAs, “I have 2 days left, would you prefer I test these new features or focus on regression testing?”. It trains them to respect my schedule and understand that it is finite. It also shows that I respect their business sense and value their opinion.
  • Your product went live and the quality sucks. Okay, you can feel somewhat guilty...along with your devs and BAs. But remember, you didn’t code or design it. Quality can only be added by the programmers (e.g., if you have no code, you have no quality.). If it sucks now, just think about how much it would have sucked before those 471 bugs you caught!
What things do you do to make testing less stressful and maintain your sanity?

"QA"

It’s like there aren’t enough testing-related terms out there so people have to just use the word “QA” to talk about anything in the testing domain.

  • “Ask QA to test this.” (It’s a group of people)
  • “QA is down again!” (It’s a test environment)
  • “We’ll need someone to QA this before it goes out.” (It’s an official action)
  • “Is it in QA”? (You’re either asking if someone is testing it or you’re asking if code resides in a specific environment)
...sigh

By speaking properly, ourselves, perhaps we can change this.

  • “Ask the testers to test this.”
  • “Environment [insert an environment name, don't name it "QA"] is down again!”
  • “We’ll need someone to test this before it goes out.”
  • "Is it being tested by the testers?"

If you read my previous post, you know I help test a product on iteration 80. This product has few automated regression tests (we are working to change that). Currently, my test team faces regression testing armed with nothing more than their brains, their hands, and a big ticking clock.

Each 4 week iteration provides us with a little less than a week to spend regression testing. If you can relate to my situation, you may be interested in two painless practices we have adopted to better handle our ever increasing challenge of regression testing.

  1. Group Regression Test Planning – We get the devs, BAs, and testers into a room and spend an hour brainstorming, to determine the top priority regression test areas of focus. We scan through the iteration's changes and draw on each other’s knowledge to create a draft of what will become the priority “1” tests or areas of focus. This occurs on a shared MS Excel regression test list spreadsheet. The prior iteration’s regression tests drop in priority...and so on.

  2. Group Regression Test Sessions – We fill a large bowl with chocolate and invite the BAs and devs to join the testers in our classroom for two 3-hour sessions of group regression testing. All participants track their progress on the shared regression test list and we tackle it as a team. The team approach also occasionally shakes out multi-user-scenario-bugs, since our product is heavily dependent on user locking.

Our approach is not to complete a set amount of regression tests before we ship. Instead, we complete as many tests as we can, within the time provided. The prioritized test list makes this possible and shields us from things outside of our control.

Is anyone else doing regression testing with mostly manual testing? How do you pull it off?

Testing updates to old software is much more difficult than testing updates to new software. The older it gets, the more cobwebs form in lonely corners, which drop out of test rotation and concern.

One of my software projects is on its 5th year of steady updates (iteration 80). In software years, this product is 80-years-old. It makes me think of my house, which happens to turn 80-years-old this year.

Seemingly easy upgrades to my old house often result in way more changes than initially planned. When my wife talked me into replacing the cracked pink bathroom tiles, I soon uncovered 6” deep concrete poured between joists that had all but rotted through (due to 79 years of direct contact with concrete.


In the 1920's, I’m sure floating concrete floors were an excellent choice for tiled floors. And fortunately, the old growth pine joists were strong enough to hold the weight…but not for 80 years.

One thing leads to another and before we knew it, we were rebuilding our entire bathroom, including the floor.


Then the changes start to expand way out of scope. The walls will not be compatible with the new floor, so those will have to be replaced (but maybe we'll just patch and replace the worst parts of the outside wall).

Then you realize older technologies are not compatible with newer. You mean Home Depot doesn’t sell Quest plumbing fittings anymore? You mean I have to replace my polybutylene pipes with copper just to move my toilet?

Meanwhile, back at work, my users were asking for the seemingly easy upgrade to allow filtering in the product’s massive control-center-like grid. Sure, no problem…oh, hold on…we can do it but the current grid won’t support it so we’ll have to rebuild the entire module, a testing nightmare (depending on your perspective).

So be careful with work estimates on seemingly simple changes to older products. And try to remember all the often ignored, dependent systems that are affected.

Yesterday a manager told me they were troubled by a showstopper bug that was found after my team had finished testing a particular build.

(My team uses the “Time’s Up!” heuristic to determine when we’re done testing.)

Then the manager asked me what I could do to prevent this from happening again. I thought long and hard on this question and just when I was about to concede defeat, the ultimate solution came to me.

It may take several iterations, but if my team can build a time machine, we can guarantee no showstopper bugs will escape. I think it will really shorten our test cycles too. We’ll just throw stuff to the users, see what problems they encounter, then travel back in time and log it as a Showstopper...or maybe we'll call it a "Show Stopped". Better yet, we’ll just explain it to dev before they write it.

I just have to work out the predestination paradox, so I don’t get stuck in a causal loop, eternally traveling back in time to prevent the same bug from occurring.


My favorite recent time travel movies:

Your application under test (AUT) probably interfaces with external systems. Fact: these external systems will go down at some point while a user is attempting to use your AUT.

Here is the obvious test:

  1. Take ExternalSystemA down. If this is outside your control, simulate ExternalSystemA’s outage by changing where your AUT points for ExternalSystemA.
  2. Trigger whatever user operations cause your AUT to interface with ExternalSystemA.
Expected Results: The user gets a friendly message indicating some functionality is blocked at this time. The support team gets an error alert indicating ExternalSystemA is not responding.



We executed the above test for 6 or 7 external systems and got our AUT robust enough to only block minimum functionality and provide good communication to users and the support team. However, just when we were getting cocky, we encountered a slight variation on the first test that crippled our AUT. Here is the test we missed for each external system.

  1. Put ExternalSystemA into a state where it is up and running but cannot respond to your AUT within the amount of time your AUT is willing to wait. Note: We were able to simulate this by taking down ExternalSystemB, which gets called by ExternalSystemA.
  2. Trigger whatever user operations cause your AUT to interface with ExternalSystemA.
Expected Results: The user gets a friendly message indicating some functionality is blocked at this time. The support team gets an error alert indicating ExternalSystemB is not responding.